Phase 1 – Green light and implementation of plan. Timings to be finalised with contractors including closure and vacating site.
Phase 2 – Move to the temporary location of the Saltash Wesley Methodist Church where a carefully selected collection of books will be available for browsing. Library users will continue to have the click and collect service available to them at the temporary location. Photocopying, printing and public computers will not be available here, however a tablet for community use will be available within the library. Established library groups and activities will be accommodated in an additional room at the Saltash Wesley Methodist Church.
As much old furniture as possible will be re-purposed that has not been planned for use in the hub.
Phase 3 – While the library will continue to function as a click and collect library and limited browsing in the interim space, new furniture, fixtures and shelving will be ordered in advance.
Phase 4 – Library building sign-off: – fit out and relocation back to the new library hub. The relocation to the new hub should take approximately two weeks from its interim location.